20250422 |
LA County |
Pico Rivera |
City Council |
Item |
9. City Hall Electric Vehicle Charging Station Project (CIP No. 50010) – Notice of
Completion. (500)
Recommendation:
1. Accept the work as completed for the City Hall Electric Vehicle Charging
Station Project - CIP No. 50010 constructed by Reliable Monitoring Services,
and authorize the City Clerk to file the Notice of Completion (NOC) with the
Los Angeles County Registrar-Recorder; and
2. Authorize the City Manager or his designee to release the retention payment
to Reliable Monitoring Services following the mandatory waiting period from
the date the NOC is recorded. |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#9
|
20250422 |
LA County |
Pico Rivera |
City Council |
Item |
7. Emergency Storm Drain Repair at 9708 Bascom Street. (500)
Recommendation:
1. Approve a resolution determining that the repair of the storm drain at 9708
Bascom Street constituted an emergency, and that it was necessary to
perform said work without the benefit of formal bidding;
2. Accept the emergency repair to the storm drain at 9708 Bascom Street,
authorize the City Manager to execute an agreement related to the
emergency storm drain repair in a form approved by the City Attorney, and
authorize payment to Sancon Technologies, Inc. (Sancon) in the amount of
$101,000; and
3. Approve the Notice of Exemption (NOE) for the subject project and authorize
the City Clerk to file the NOE with the County recorder, in accordance with
the California Environmental Quality Act (CEQA).
Resolution No. ____ A RESOLUTION OF THE CITY COUNCIL OF THE |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#7
|
20250422 |
LA County |
Pico Rivera |
City Council |
Item |
6. Crimson California Pipeline – Franchise Renewal Setting Public Hearing Date.
Recommendation: (500)
1. Approve a resolution initiating the renewal of the Crimson California, L.P.
pipeline franchise by setting May 27, 2025, as the date for the public hearing
for the first reading of the renewal ordinance, which is within the required 20-
to-60-day period following passage of the resolution; and
2. Direct the City Clerk to publish the Notice of Public Hearing at least once
within fifteen (15) days after the passage of the resolution in a newspaper of
general circulation.
Resolution No. ____ A RESOLUTION OF THE CITY COUNCIL OF THE |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#6
|
20250422 |
LA County |
Pico Rivera |
City Council |
Item |
19. Pico Park Prefabricated Restroom Project (CIP No. 50085) – Award
Construction. (500)
Recommendation:
1. Approve the plans and specifications for the Pico Park Prefabricated
Restroom Project (CIP No. 50085);
2. Award a Construction Contract for a not-to-exceed amount of $135,920 to
Diamond Construction & Design for the Pico Park Prefabricated Restroom
Project, CIP No. 50085; and authorize the City Manager to execute the
contract in a form approved by the City Attorney;
3. Authorize the City Manager or his designee, to approve change orders, as
needed, in an amount not-to-exceed $20,400 (approximately 15% of the total
contract amount) for construction contingency; and
4. Approve the Notice of Exemption (NOE) for the subject project and authorize
the City Clerk to file the NOE with the County Recorder, in accordance with
the California Environmental Quality Act.
Agreement No. ________ |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#19
|
20250422 |
LA County |
Pico Rivera |
City Council |
Item |
18. Smith Park Field Fencing Replacement (CIP No. 50104). (500)
4-22-2025 Agenda City Council
Recommendation:
1. Award a General Services Agreement to C&O Manufacturing for the
installation of new fencing for Smith Park Sports Field in the amount of
$188,800, and authorize the City Manager to execute the agreement in a
form approved by the City Attorney;
2. Authorize the City Manager, or his designee, to approve change orders, as
needed, in an amount not-to-exceed $18,000 (approximately 10% of the total
contract amount) for construction contingency;
3. Transfer $56,800 from Smith Park Security System Project (Account No.
400.70.7310-54500-CIP50092) to Smith Park Fencing Replacement
(Account No. 400.70.7300-54500-CIP50104); and
4. Approve the Notice of Exemption (NOE) for the subject project and authorize
the City Clerk to file the NOE with the County Recorder, in accordance with
the California Environmental Quality Act.
Agreement No. ________ |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#18
|
20250422 |
LA County |
Pico Rivera |
City Council |
Item |
11. Washington Boulevard Bridge Repair Project (CIP No. 50120) – Notice of
Completion. (500)
Recommendation:
1. Accept the work as completed for the Washington Boulevard Bridge Repair
Project - CIP No. 50120 (Project) constructed by Griffith Construction
Company and authorize the City Clerk to file the Notice of Completion (NOC)
with the Los Angeles County Registrar-Recorder; and
2. Authorize the City Manager or his designee to release the retention payment
to Griffith Construction Company following the mandatory waiting period
from the date the NOC is recorded. |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#11
|
20250422 |
LA County |
Pico Rivera |
City Council |
Item |
10. Telegraph Road Bridge Guardrail Repair Project (CIP No. 50119) – Notice of
Completion. (500)
Recommendation:
1. Accept the work as completed for Telegraph Road Bridge Guardrail Repair
Project - CIP No. 50119 (Project) constructed by Riverside Construction and
authorize the City Clerk to file the Notice of Completion (NOC) with the Los
Angeles County Registrar-Recorder; and
2. Authorize the City Manager or his designee to release the retention payment
to Riverside Construction following the mandatory waiting period from the
date the NOC is recorded. |
April 22, 2025
LA County
Pico Rivera
City Council
Item
#10
|