Award Service Agreements for the Construction of the Cathedral City,
Mountain Cathedrals Entryway Monument Project (C02601)
Recommendation:
Staff is presenting two (2) alternative recommendations for City Council
consideration.
Option 1 (Recommendation for Solar Powered System)
To:
• Award a service agreement to Hoffman Steel Fabrication, Inc. in the
amount of $69,431.00 for the fabrication and installation of the
Cathedral City, Mountain Cathedrals Entryway Monument Project
(C02601);
• Award a service agreement to Westcon Construction Services, Inc. in
the amount of $24,500.00 for construction of the foundation for the
Mountain Cathedrals Entryway Monument;
• Approve the proposal from Hot Purple Energy in the amount of
$6,500.00 to upgrade the existing solar system and install electrical
components; and
• Approve a fifteen percent (15%) contingency in the amount of
$15,064.65 for unforeseen construction costs;
• Approve a budget amendment to Gas Tax (50%) and Measure A
(50%) in the amount of $9,599.91 to establish a combined
construction budget totaling $115,495.65 for the Cathedral City
Mountain Cathedrals Entryway Monument Project (C02601);
• Authorize the City Manager to execute the service agreements; and,
• Authorize the City Engineer to execute the proposal with Hot Purple
Energy, request bonds and insurances and issue notices to proceed.
Option 2 (Recommendation for Hard-Wired System)
To:
• Award a service agreement to Hoffman Steel Fabrication, Inc. in the
amount of $69,431.00 for the fabrication and installation of the
Cathedral City, Mountain Cathedrals Entryway Monument Project
(C02601); and,
• Award a service agreement to Westcon Construction Services, Inc. in
the amount of $24,500.00 for construction of the foundation for the
Mountain Cathedrals Entryway Monument; and,
• Approve the proposal from Towers Electric in the amount of
$24,582.15 for installation of underground conduits across East Palm
Canyon Drive; and,
• Approve the proposal from Rhythm Electric LLC, in the amount of
$5,050.00 for installation of power and electrical components for the
mountain Cathedrals Entryway Monument; and,
• Approve a fifteen percent (15%) contingency in the amount of
$18,534.47 for unforeseen construction costs; and,
• Approve a budget amendment to the Gas Tax (50%) and Measure A
(50%) in the amount of $36,201.88 to establish a combined
construction budget totaling $142,097.62 for the Cathedral City,
Mountain Cathedrals Entryway Monument Project (C02601); and,
• Authorize the City Manager to execute the service agreements; and,
• Authorize the City Engineer to execute proposals with Towers Electric
and Rhythm Electric Inc., request bonds and insurances and issue
notices to proceed. |
January 28, 2026
Riverside County
Cathedral City
City Council
Order of Business 5
#B
|
| 20260128 |
Riverside County |
Cathedral City |
City Council |
Order of Business 5 |
A.
Traffic Signal Head Backplates Change Order Request for the HSIP
Cycle 11C - Citywide Traffic Signal Hardware Upgrades Project
(C08756)
Recommendation: To approve Change Order No. 1 to the contract with
Econolite Systems, Inc., in the amount of $107,129.84; for the construction of
HSIP 11C, Citywide Traffic Signal Hardware Upgrades Project (C08756);
and, authorize a budget adjustment to the construction budget for the project,
in the amount of $47,875.11; and, authorize the City Engineer to execute the
change order and issue the notice to proceed for this work. |