Downey

City Council

December 10, 2024 Item #3

Agenda Item 3

3. APPROVAL OF A CONSTRUCTION CONTRACT FOR THE WOODRUFF AVENUE STREET\nIMPROVEMENT PROJECT, PHASE 2 BETWEEN WASHBURN ROAD AND FOSTER ROAD,\nCAPITAL IMPROVEMENT PROJECT (CIP) NO. 14-14B: Public Works.\nTHAT THE CITY COUNCIL:\n1) AWARD CAPITAL IMPROVEMENT PROJECT NO. 14-14B TO SEQUEL CONTRACTORS,\nINC., THE LOWEST RESPONSIVE, RESPONSIBLE BIDDER FOR THE TOTAL BID\nAMOUNT OF $5,052,110 AND WAIVE ANY AND ALL MINOR IRREGULARITIES IN THE\nBIDDING DOCUMENTS AS SUBMITTED BY SAID BIDDER;\n2) AUTHORIZE THE CITY MANAGER, OR HIS DESIGNEE, TO EXECUTE THE\nCONSTRUCTION CONTRACT WITH SEQUEL CONTRACTORS, INC. IN THE AMOUNT\nOF $5,052,110, INCLUDING ANY NON-SUBSTANTIVE EXTENSIONS, CHANGE ORDERS\nAND AMENDMENTS UP TO THE AUTHORIZED BUDGET AMOUNT OF $6,231,321; AND,\n3) APPROVE AN APPROPRIATION IN THE AMOUNT OF $4,179,081 FROM ACCOUNT NO.\n15-1-6711-0520.