El Monte

City Council

March 21, 2023 Order of Business 14 #5

Agenda Item 5

14.5 Consideration and Approval of a Construction Contract with CT&T Concrete Paving\nInc. for the Sidewalk & Curb Ramp Reconstruction Project (Phase 2), CIP 052, for a\nNot-to-Exceed Amount of $528,404.25.\nRECOMMENDATION OF BUSINESS ITEM UNDER CONSIDERATION:\nIt is recommended that the City Council:\n1. Consider and approve a Construction Contract with CT&T Concrete Paving, Inc. for the\nSidewalk & Curb Ramp Reconstruction Project (Phase 2), CIP 052 (the “Project”) for a\nnot-to-exceed amount of $528,404.25 which includes a Contract amount of $480,367.50\nplus a 10% contingency of $48,036.75;\n2. Consider and approve the additional appropriation in the amount of $91,000; and\n3. Authorize the City Manager or her designee, to execute the Construction Contract with\nCT&T Concrete Paving, Inc.\nTotal Cost: $528,404.25 Account No: 220-67-052-8221 - $528,404.25\nCDBG Funds\n$ 91,000.00 225-67-052-8221\nIs the cost of this item budgeted? Yes Measure M Funds