May 13, 2026 Item #8

Agenda Item 8

Approve Change Order No. 1 for the Flood Plain Trail Erosion Repair Project\nand Increase Construction Contingency Authority\nRecommendation:\nThe City Council:\n1. Authorize Change Order No. 1 to the Hardy and Harper Inc. construction\ncontract for the Flood Plain Trail Erosion Repair Project in the amount of\n$26,267.00;\n2. Increase the total authorized construction contract amount from $93,095.00 to\n$119,362.00;\n3. Authorize staff to approve change orders not to exceed 20% of the revised\ncontract amount ($23,872.40); and\n4. Authorize staff to approve and process payments to Hardy & Harper Inc. for\nconstruction services.