17. 26-561 Accept Lowest Responsive and Responsible Bid and Award
Construction Contract to Sequel Contractors, Inc. in the Amount of
$6,783,480 for the 2025 Arterial Rehabilitation Project (CC1771)
Recommended Action:
A) Accept the lowest responsive and responsible bid submitted by Sequel Contractors,
Inc. in the amount of $6,783,480; and,
B) Authorize the Director of Public Works to approve change orders up to 10%
contingency in potential construction change orders; and,
C) Approve the appropriation of $682,737 to account 125490002.82300; and,
D) Authorize the Mayor and City Clerk to execute a construction contract in a form
approved by the City Attorney.