30. Fire Station Remodel and Refurbishment Projects Construction Contract
Recommendation: Approve the four proposed Fire Station Remodel and
Refurbishment Projects (Projects) as follows: Fire Station 58 General
Improvements Project, Capital Project (CP) No. 89059, with a total project
budget of $1,726,000; Fire Station 70 Privacy and Access-Malibu Project, CP
No. 89077, with a total project budget of $1,226,000; Fire Station 110-Marina
del Rey Privacy and Access Refurbishment project, CP No. 89020, with a total
project budget of $3,410,000; and Fire Station 151 Privacy and
Access-Glendora project, CP No. 89075, with a total project budget of
$1,670,000. Approve the appropriation adjustment transferring $3,561,000 of
Accumulated Capital Outlay Funds from the Fire Districtʹs Privacy and Access
Phase II, Capital Project No. 88946, as follows: $967,000 to the Fire Station 58
General Improvements project, Capital Project No. 89059; $662,000 to the Fire
Station 70 Privacy and Access-Malibu project, Capital Project No. 89077;
$1,040,000 to the Fire Station 110-Marina del Rey Privacy and Access
Refurbishment project, Capital Project No. 89020; and $892,000 to the Fire
Station 151 Privacy and Access Glendora project, Capital Project No. 89075, to
fully fund the proposed projects. Authorize the Director of Public Works to
carry out, manage, and deliver the Projects on behalf of the Consolidated Fire
Protection District of the County; award and execute construction agreements,
amendments, and supplements within the same authority and limits delegated to
the Director by the Board for County Capital Improvement Projects; accept the
Projects; and release retention upon acceptance. Authorize the Director to
deliver the proposed Projects using Board-approved Job Order Contracts. Find
the four proposed Projects are exempt from the California Environmental Quality
Act. (Supervisorial Districts 2, 3 and 5) (Department of Public Works)