26. Harbor-UCLA Medical Center Replacement Program Construction-Related
Contract
Recommendation: Find that the scope of work to be carried out by the
proposed change orders is within the scope of the environmental impacts
analyzed in the previously certified Final Environmental Impact Report and
subsequent Addenda Nos. 1, 2, and 3 for the Harbor-UCLA Medical Center
Campus Master Plan. Approve and authorize the Director of Public Works to
finalize negotiations and execute a change order with Hensel Phelps
Construction Company, for a not-to-exceed amount of $1,000,000, to design
and construct an auxiliary generator yard at Surface Lot 2. Approve and
authorize the Director to finalize negotiations and execute a change order with
Hensel Phelps Construction Company, for a not-to-exceed amount of
$15,000,000, an increase of $4,677,655 from the previously Board-approved
change order amount of $10,322,345, to design and construct utility ductbank
and a utility bridge between the new Central Utility Plant and the existing
Surgery/Emergency Building. There is no Net County Cost impact associated
with the recommended actions. (Supervisorial District 2) (Department of