35. Boilers and Chillers Replacement Project
Recommendation: Approve a revised project budget of $46,100,000, an
increase of $21,200,000 from the previous Board approved amount of
$24,900,000, for the demolition and make-ready work on the Civic Center
Central Plant Boiler and Chillers Replacement Project, Capital Project No.
87735 (Project) (1); award and authorize the Director of Public Works to
execute an architectural/engineering agreement with Perkins Eastman
Architects, D.P.C., for the design of the Project at an amount not to exceed
$6,100,000 for the duration of the Project until final acceptance by the County;
supplement the contract amount by up to 25% based on the Project's needs;
authorize the Director of Internal Services, as the County's Purchasing Agent,
to carry out the required processes for procurement and acquisition of long
lead mechanical and electrical equipment for the Project at an amount not to
exceed $6,000,000; and find that the recommended actions are within the
scope of the previous exemption from the California Environmental Quality Act.
(Department of Public Works) APPROVE 4-VOTES (23-0015)