3. RESOLUTION NO. ____________ - ORDER APPROVING COMPENSATION RESET
UNDER PERMIT NO. 827 WITH APM TERMINALS PACIFIC, LLC
Summary: Staff requests approval of the Order resetting compensation under Permit No. 827
(Permit) between the City of Los Angeles Harbor Department (Harbor Department) and APM
Terminals Pacific, LLC (APMT). The reset covers the five-year period from August 1, 2022,
through July 31, 2027. As a result of this Order, total annual guaranteed compensation will
increase by at least $93.7 million, or 23.4 percent, from $401.1 million over the prior five-year
period to $494.8 million over the next five-year period. Provided below is a summary:
• Minimum Annual Guarantee (MAG) per acre of the container terminal premises
(441.74 acres) will increase from $185,000 to $210,000.
• Annual rent for the intermodal rail facility (40.84 acres) will increase from $2,032,525
per year as of July 31, 2022, to the following rate schedule:
o August 1, 2022: $2,175,615
o August 1, 2023: $2,175,615
o August 1, 2024: $2,175,615
o August 1, 2025: $2,318,772
o August 1, 2026: $3,220,152
• Per container charge rate schedule (i.e., TEU rate) reflects a wholesale 7.04 percent
increase consistent with the General Rate Increase which took effect August 1, 2022.
Effective August 1, 2023, the MAG and TEU rates will be subject to annual increases based
upon changes in the Consumer Price Index (CPI), subject to an annual minimum of 2 percent
and a maximum of 7 percent.
Recommendation: Board resolve to (1) find that the Director of Environmental Management has
determined that the proposed action is administratively exempt from the requirements of the
California Environmental Quality Act (CEQA) under Article II Section 2(f) of the Los Angeles City
CEQA Guidelines; (2) approve the Order resetting compensation under Permit No. 827 with
APM Terminals Pacific, LLC for the period of August 1, 2022 to July 31, 2027; (3) authorize the
Board Secretary to attest to the Order resetting compensation under Permit No. 827; and (4)
adopt Resolution No.___________ and Order No.____________.