Agenda Item
· Poway
City Council — Item 7
Original agenda text
Item
7. Acceptance of the Lester J. Berglund Water Treatment Plant Clearwell Bypass Project, Bid No. 21020 with G.S.E. Construction Company, Inc. as Complete and Update on the Water Infrastructure
Improvement Program
City Manager’s Recommendation: It is recommended the City Council 1) accept the Lester J.
Berglund Water Treatment Plant Clearwell Bypass Project as complete; 2) authorize the City Clerk
to file and record the Notice of Completion; 3) authorize the release of the retention in the amount
of $379,131.75 if unencumbered, 45 days after City Council acceptance; 4) release the Fidelity and
Deposit Company of Maryland Bond for Material and Labor in the amount of $7,273,700.00 after
the release of retention; and 5) retain the Fidelity and Deposit Company of Maryland Bond for
Faithful Performance for a period of one year.