2. RESOLUTION NO. ____________ - APPROVAL OF FIRST AMENDMENT TO
MASTER JOINT REVOCABLE PERMIT NO. 09-17 AMONG PACIFIC PIPELINE
SYSTEM LLC AND CITY OF LOS ANGELES HARBOR DEPARTMENT AND
PORT OF LONG BEACH, AS JOINT OWNERS
Summary: Staff requests approval of the First Amendment (Amendment) to Master Joint
Revocable Permit No. 09-17 (MJRP) among Pacific Pipeline System LLC (Pacific), the
City of Los Angeles Harbor Department (Harbor Department or POLA), and the Port of
Long Beach (POLB, and with POLA collectively Ports), as joint owners, for subsurface
pipeline facility segments owned and maintained by Pacific covering 13,075 square feet
of area along the Alameda Corridor in Wilmington, Carson, and Compton; and on the
San Pedro Branch line in Wilmington, Long Beach, and South Gate. Staff further
requests approval of Pacific’s parent guaranty from Plains All American Pipeline, L.P
(Parent Guaranty).Under the First Amendment, the following substantive changes are
made to the MJRP: 1) adds facilities located in the Ports’ right-of-way not previously
included in the MJRP, increasing the total permit area from 8,935 square feet to 13,075
square feet; 2) increases the monthly compensation to account for the addition of new
facilities and an adjustment to market rates; 3) revises the facilities index exhibits to list
additional facilities and expansion in square footage of the premises area; 4) updates
the map exhibit per the revised facilities index; and 5) adds a corporate guaranty from
Pacific’s parent entity. Currently, the Harbor Department receives rent of $389.51 per
month under the MJRP. Under the proposed First Amendment, monthly rent will
increase by $839.91, or 216 percent, to $1,229.42 per month, or $14,753.04 per year,
retroactive to 2018. Annual rent increases based upon the Consumer Price Index (CPI)
will be retroactively applied beginning in 2019, and annually thereafter. The First
Amendment requires approval from both Ports’ Board of Harbor Commissioners. The
POLB Board of Harbor Commissioners approved this Amendment at its meeting held on
March 24, 2022.
Recommendation: Board resolve to (1) find that the Director of Environmental
Management has determined that the proposed action is categorically exempt from the
requirements of the California Environmental Quality Act (CEQA) under Section 15301
of the State CEQA Guidelines; (2) approve the First Amendment to Master Joint
Revocable Permit No. 09-17 among Pacific Pipeline System LLC and the City of Los
Angeles Harbor Department and Port of Long Beach, as joint owners; (3) authorize the
Executive Director to execute and the Board Secretary to attest to the First Amendment
to Master Joint Revocable Permit No. 09-17; (4) approve the Parent Guaranty provided
by Plains All American Pipeline, L.P. for Master Joint Revocable Permit No. 09-17; and
(5) adopt Resolution No.____________.