Agenda Item
· El Monte
City Council — Item 4
Original agenda text
Order of Business 14
14.4 Consideration and Approval of a Professional Services Agreement with Michael Baker
International for Design Services for the Valley Boulevard and Main Street Complete
Streets Feasibility Studies, CIP No. 063 and CIP No. 078 for a Not-to-Exceed Amount
of $631,095.78.
RECOMMENDATION OF BUSINESS ITEM UNDER CONSIDERATION:
It is recommended that the City Council:
1. Consider and approve a Professional Services Agreement (PSA) for Design Services for
the Valley Boulevard Complete Streets Feasibility Study, CIP No. 063 (the “Project”) with
Michael Baker International for a not-to-exceed amount of $395,655.92 which includes
an Agreement amount of $59,687.20 plus a ten percent (10%) contingency of
$35,968.72;
2. Consider and approve a Professional Services Agreement (PSA) for Design Services for
the Main Street Complete Streets Feasibility Study, CIP No. 078 (the “Project”) with
Michael Baker International for a not-to-exceed amount of $235,439.86 which includes
an Agreement amount of $214,036.24 plus ten percent (10%) contingency of $21,403.62;
3. Authorize the appropriation Metro funds in the amount of $395,655.92 for the Valley
Boulevard Complete Streets Feasibility Study, CIP No. 063 and $235,439.86 for the Main
Street Complete Streets Feasibility Study, CIP No. 078 for a total appropriation of
$631,095.78; and
4. Authorize the City Manager, or her designee, to execute the two (2) Professional Services
Agreements with Michael Baker International.
Total Cost: $631,095.78 Account No: 212-67-063-6111 - $395,655.92
Valley
212-67-078-6111 - $235,439.86
Is the cost of this item budgeted? Yes Main Metro Funds