Agenda Item
· San Diego
City Council — Item 02
Original agenda text
Item
Item 102: Award a Consultant Agreement, Contract #H2225964, to Hazen and Sawyer to
Provide Professional Design and Construction Support Services for the Otay 2nd
Pipeline Phase 5 Replacement Project.
Total Estimated Cost of Proposed Action and Funding Source:
The phase funded agreement with Hazen and Sawyer is in the total amount not-to-exceed
$3,247,222, of which $2,174,437, is for the first phase and $1,072,785, is for all
subsequent phases.
Council District(s) Affected: 4.
https://sandiego.hylandcloud.com/211agendaonlinecouncil/Meetings/ViewMeeting?id=5434&doctype=1&site=council 13/25
3/2/23, 3:48 PM View Meeting - OnBase Agenda Online
Proposed Actions:
Subitem-A: (R-2023-413)
Resolution determining that the award and execution of the consultant agreement with
Hazen and Sawyer to provide professional design and construction support services for
the Otay 2nd Pipeline Phase 5 Project is statutorily exempt from CEQA pursuant to State
CEQA Guidelines section 15262.
Subitem-B: (R-2023-391) (Rev. 2/24/23)
Resolution authorizing award and execution of the consultant agreement with Hazen and
Sawyer for professional design and construction support services for the Otay 2nd
Pipeline Phase 5 Replacement Project and taking related actions.
Committee Actions Taken:
This item was heard at the Active Transportation and Infrastructure Committee meeting
on January 25, 2023.
ACTION: Motion by Committee Member Montgomery Steppe, second by Vice Chair
LaCava, to recommend Council approval of staff's proposed actions.
VOTE: 4-0; Lee-yea, LaCava-yea, Montgomery Steppe-yea, von Wilpert-yea.
Engineering & Capital Projects: Elif Cetin, (619) 533-3794
City Attorney Contact: Adam Wander