Agenda Item
· San Gabriel
City Council — Item H
Original agenda text
Order of Business 4
H. ADDITIONAL FUNDING IN THE AMOUNT OF $350,000 FOR THE SEWER
PUMP STATION PROJECT
Construction of the Sewer Pump Station is currently in progress and scheduled
to be completed by April 2023. The original construction cost for this project
was $845,000 with a $84,500 contingency totaling $929,500. Two unforeseen
circumstances have arisen during construction, necessitating an increase of
$350,000 in the project budget through Council’s adoption of a Resolution.
There is a balance of $113,559 available in the adopted Fiscal Year 2022-2023
budget via the Capital Improvement Project 4-20-01 Sewer Pump Station
Improvements using sewer fund budget account 122-800-38-97-403. The total
project costs for this item is $1,279,500, which is paid from the sewer fund.
California Environmental Quality Act (CEQA) Determination: Not a Project as
defined in Section 15378 of the State CEQA Guidelines.
Recommended Action:
Staff recommends that the City Council approve Resolution No. 23-20 to
appropriate $236,441 from the Sewer Fund to account 122-800-38-97-403; and
authorize the City Manager to execute a Change Order to increase the Project
Purchase Order No. 8942 by an additional $236,441 for a total project amount
of $1,279,500.