Agenda Item
· Los Angeles
LA County Board — Item 35
Original agenda text
Item
35. Beverly Boulevard Traffic Signal Synchronization Program - Pomona
Boulevard to Pickering Avenue Construction Contract
Recommendation: Adopt resolutions finding that the modification and
synchronization of traffic signals in the Cities of Montebello, Pico Rivera,
Whittier, and in the unincorporated community of East Los Angeles is of
general County interest and that County aid in the form of
Highways-Through-Cities Funds in the amount of $2,289,500, will be provided
to the Cities of Montebello, Pico Rivera, and Whittier; approve and authorize the
Director of Public Works to sign Funding Cooperative Agreements between the
County and the Cities of Montebello, Pico Rivera, and Whittier to allow the
Cities to contribute their share of funding to the Beverly Boulevard Traffic Signal
Synchronization Program - Pomona Boulevard to Pickering Avenue Project
(Project) (1 and 4), with a total Project amount currently estimated to be
$5,447,400, with the City of Montebello’s share estimated to be $2,596,000, the
City of Pico Rivera’s share estimated to be $478,500, the City of Whittier’s
share estimated to be $1,369,400, and the County’s share estimated to be
$1,003,500, and execute amendments and modifications to the Funding
Cooperative Agreements to incorporate necessary programmatic and
administrative changes; approve the Project and adopt the plans and
specifications for the Project at an estimated construction contract amount
between $2,400,000 and $3,600,000; advertise for bids to be received before
11:00 a.m. on April 18, 2023; find pursuant to Public Contract Code Section
3400 (c) (2) that it is necessary to specify the designated items by specific
brand name in order to match other products in use on a particular public
improvement either completed or in the course of completion; find that the
proposed Project is exempt from the California Environmental Quality Act; and
authorize the Director of Public Works to take the following actions:
(Department of Public Works) ADOPT 4-VOTES
Determine whether the bid of the apparent responsible contractor with
the lowest apparent responsive bid is, in fact, responsive and, if not
responsive, to determine which apparent responsible contractor
submitted the lowest responsive bid;
Award and execute a construction contract for the Project with the
responsible contractor with the lowest responsive bid within or less than
the estimated cost range of $2,400,000 and $3,600,000, or that exceeds
the estimated cost range by no more than 15% if additional and
appropriate funds have been identified; and
Extend the date and time for the receipt of bids, allow substitution of
subcontractors and relief of bidders, approve and execute change orders
within the same monetary limits delegated to the Director, and release
retention money withheld. (23-1107)
Attachments: Board Letter
Public Comment/Correspondence