15. Award a Construction Contract to Pacific Hydrotech Corp. in the Amount of $12,795,865 for the Well 32 Rehabilitation Project, with an Estimated Project Delivery Cost of $16,634,625 (Project No. 13-6433) (Non-General Fund) Department(s): Public Works Agency Recommended Action: 1. Award a construction contract to Pacific Hydrotech Corp., the lowest responsible bidder, in accordance with the base bid in the amount of $12,795,865 for construction of the Well 32 Rehabilitation Project, for a term beginning May 2, 2023, and ending upon project completion, and authorize the City Manager to execute the contract subject to non-substantive changes approved by the City Manager and the City Attorney. 2. Approve the Project Cost Analysis for a total estimated construction delivery cost of $16,634,625, which includes $12,795,865 for the construction contract, $1,224,820 for contract management, $694,560 for contract administration, inspection, and testing, and a $1,919,380 project contingency for unanticipated or unforeseen work.