Agenda Item
· Los Angeles
LA County Board — Item 47
Original agenda text
Item
47. Willowbrook 2 Project Affordable Housing and Sustainable Communities
Construction Contract
Recommendation: Approve the Willowbrook 2 Project Affordable Housing and
Sustainable Communities Project (Project) and adopt the plans and
specifications at an estimated construction contract amount between
$3,100,000 and $4,600,000; advertise for bids to be received before 11:00 a.m.
on May 30, 2023; find pursuant to State Public Contract Code, Section 3400
(c) (2), that it is necessary to specify the designated items by specific brand
name in order to match other products in use on a particular public
improvement either completed or in the course of completion; find that the
recommended actions are within the scope of the County of Los Angeles 2012
Bicycle Master Program Environmental Impact Report previously certified by
the Board, or are exempt from the California Environmental Quality Act; and
authorize the Director of Public Works to take the following actions:
(Department of Public Works) ADOPT
Determine whether the bid of the apparent responsible contractor with
the lowest apparent responsive bid is, in fact, responsive and, if not
responsive, determine which apparent responsible contractor submitted
the lowest responsive bid;
Award and execute a construction contract for the Project with the
responsible contractor with the lowest responsive bid within or less than
the estimated cost range, or that exceeds the estimated cost range by no
more than 15%, if additional and appropriate funds have been identified;
and
Extend the date and time for the receipt of bids, allow substitution of
subcontractors and relief of bidders, approve and execute change orders
within the same monetary limits delegated to the Director; accept the
Project upon its final completion, and release retention money withheld.
(23-1643)
Attachments: Board Letter
Public Comment/Correspondence