Agenda Item
· Bell Gardens
City Council — Item 10
Original agenda text
Item
10. EXTENSION OF PROFESSIONAL SERVICES AGREEMENTS FOR ENGINEERING AND
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES
The purpose of the John Anson Ford Park Infiltration Cistern Project (the “Project”) is to comply
with stormwater regulations set forth by the Los Angeles Regional Water Quality Control Board
(LARWQCB) under the Municipal Separate Stormwater Sewer System, the MS4 Permit. The
Project will capture trash, nutrients, heavy metals, bacteria, and reduce toxicity in the urban runoff
from the watershed by installing stormwater and dry weather flow diversion pre-treatment, retention,
and infiltration facilities that will capture and infiltrate the stormwater runoff prior to it reaching the Rio
Hondo. The project has had various change order and due to a delay in completion, John L. Hunter
and Associates, who provide project and construction management services and CWE
Corporation, the engineer of record providing engineering support since the start of the project, will
require extensions to their existing agreements.
Recommendation:
It is staff's recommendation that the City Council by motion:
1. Extend the existing Agreement with John L. Hunter and Associates (JLH) through September
30, 2024, and approve additional appropriations of $658,000 to allow for completion of the
John Anson Ford Park Infiltration Cistern Project; and
2. Extend the existing Agreement with CWE Corporation (CWE) through September 30, 2024,
and approve additional appropriations of $75,000 to allow for completion of the John Anson
Ford Park Infiltration Cistern Project.
DISCUSSION (Items Nos. 11 - 12)