4. RESOLUTION NO. ____________ - APPROVAL OF A COST SHARE AGREEMENT
BETWEEN THE CITY OF LOS ANGELES HARBOR DEPARTMENT AND THE PORT
OF LONG BEACH TO FUND A TECHNOLOGY ADVANCEMENT PROGRAM PROJECT
WITH SSA TERMINALS, LLC
Summary: Staff requests approval of the proposed Cost Share Agreement between the City of
Los Angeles Harbor Department (Harbor Department) and the Port of Long Beach (POLB) to
fund a Clean Air Action Plan (CAAP) Technology Advancement Program (TAP) project with SSA
Terminals, LLC (SSA) to design, manufacture, and demonstrate two zero-emission Hybrid
Hydrogen Fuel Cell (HFC) Top Handlers (Project). The total cost of the Project is $6,482,295.
TAP funding in the amount of $2,191,000 will be split equally between the Harbor Department
and POLB. SSA and their project team will be responsible for the remaining costs as part of the
manufacturing of the top handlers and the demonstration at SSA’s POLB terminal. As lead
agency, POLB has already entered into an agreement with SSA to implement the Project. If the
proposed Cost Share Agreement is approved, then the Harbor Department would be financially
responsible for funding $1,095,500 of the proposed TAP amount.
Recommendation: Board resolve to (1) find that the Director of Environmental Management has
determined that the proposed action is administratively and categorically exempt from the
requirements of the California Environmental Quality Act (CEQA) under Article II Section 2(f)
and Article III Class 6(2) of the Los Angeles City CEQA Guidelines; (2) approve the Cost Share
Agreement between the City of Los Angeles Harbor Department and the Port of Long Beach for
the reimbursement of $1,095,500 for the SSA HFC Top Handlers Project; (3) authorize the
Executive Director to execute and Board Secretary to attest to said agreement for and on behalf
of the Board of Harbor Commissioners; and (4) adopt Resolution No.____________.