18. NOTICE OF COMPLETION: CIVIC CENTER LIBRARY ROOF RESTORATION –
F2M22-55, C2M22-66, M2M23-105
On December 12, 2022, the City Council awarded a contract to Best Contracting Services
to restore the Library’s roof in the amount of $623,871. The final cost of the project was
$623,871 per the contract amount. The project has been completed in accordance with
the City’s requirements and specifications. As such, it would be appropriate for the City
Council to accept the project as complete and instruct the City Clerk that the Notice of
Completion be filed with the County of Los Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Best Contracting Services
to restore the Library’s roof as complete in the amount of $623,871; direct the City Clerk
to file a Notice of Completion with the County of Los Angeles for recordation; direct the
Finance Director to release the retention 35 days from the date of recordation if no liens
are filed; and, direct staff to undertake the steps necessary to finalize Council’s action.
(M2M23-105)