15. NOTICE OF COMPLETION: FREMONT AVE SERIES TO MULTIPLE CIRCUIT
CONVERSION – CONDUIT INSTALLATION PROJECT – F2M22-16, K2M22-335,
M2M23-103
On July 12, 2022, staff issued a contract to Yunex, LLC (K2M22-335) for the construction
of the Conduit Installation for the Fremont Ave Series to Multiple Circuit Conversion in the
amount of $37,945.00. During construction, which requires Southern California Edison
(SCE) inspection, sign-off and construction assistance, it was determined additional
preparation of the work site was necessary to complete the SCE portion of the project.
This additional work was an unforeseen change from the original scope of work contracted
between the City and Yunex, LLC. The additional work to complete the project increased
the contract amount by $14,795.00, bringing the total to $52,740.00. On December 12,
2022, City Council authorized an amendment to contract K2M22-335 with Yunex, LLC to
increase the total amount of the contract to $52,740.00. This project has been inspected
by staff and all work has been completed in accordance with the City’s requirements and
specifications. As such, it would be appropriate for the City Council to accept this project
as complete and instruct that the Notice of Completion be filed with the County of Los
Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Yunex, LLC for the
construction of the Conduit Installation for the Fremont Ave Series to Multiple Circuit
Conversion, for the installation of LED street lighting as complete in the amount of
$52,740; direct the City Clerk to file a Notice of Completion with the County of Los Angeles
for recordation; instruct the Finance Director to release the 5% retention 35 days from the
date of recordation if no liens are filed; and, direct staff to undertake the steps necessary
to finalize Council’s action. (M2M23-103)