13. Approve an Appropriation Adjustment and Award a Construction Contract to Legion
Contractors, Inc. in the Amount of $3,366,625 for the Standard – McFadden Park
Project, with an Estimated Project Delivery Cost of $4,208,281 (Project No. 202729)
(NonGeneral Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve an appropriation adjustment to recognize
$669,060 in revenue received from prior years into the Residential Development
District 3, Park Acquisition & Development Fees revenue account and appropriate
the same amount into the Residential Development District 3, Improvements Other
Than Building expenditure account. (Requires five affirmative votes)
2. Approve an amendment to the FY 202324 Capital Improvement Program to
include $669,060 in construction funds for the Standard – McFadden Park Project
(Project No. 202729).
3. Award a construction contract to Legion Contractors, Inc., the lowest responsible
bidder, in accordance with the base bid in the amount of $3,366,625, subject to
change orders (not to exceed 25 percent of the base bid amount) in accordance with
the Greenbook: Standard Specifications for Public Works Construction, for
construction of the Standard – McFadden Park Project, for a term beginning
September 19, 2023 and ending upon project completion, and authorize the City
Manager to execute the contract subject to nonsubstantive changes approved by the
City Manager and the City Attorney.
4. Approve the project cost analysis for a total estimated construction delivery cost
of $4,208,281, which includes $3,366,625 for the construction contract; $504,994 for
contract administration, inspection, and testing; and a $336,662 project contingency
for unanticipated or unforeseen work.