Agenda Item
· Santa Monica
City Council — Item F
Original agenda text
Order of Business 5
F. Award Construction and Construction Management Contracts for Fiscal Year 2023-2024 Annual Street
Paving and Sidewalk Repair Project
Recommended Action
Staff recommends that the City Council:
1. Adopt a finding of Categorical Exemption pursuant to Section 15301
of the California Environmental Quality Act (CEQA) Guidelines.
2. Award Bid #SP2680 to Sully-Miller Contracting Company for construction services for the
Fiscal Year 2023-2024 Annual Street Paving and Sidewalk Repair Project for the Public
Works Department.
3. Authorize the City Manager to negotiate and execute a contract with Sully-Miller
Contracting Company in an amount not to exceed $2,853,346 (including a 10%
contingency).
4. Authorize the Director of Public Works to issue any necessary change orders to complete
additional work within contract authority.
5. Award Request for Proposals (RFP) #SP2680 to PSOMAS to provide construction
management, observation, and material testing services for the FY 2023-24 Annual Street
Paving and Sidewalk Repair Project and the Street Lighting Modernization Program -
Package 3 Project for the Public Works Department.