Santa Ana
City Council
18.
Approve Appropriation Adjustments and Award a Construction Contract to
C.S. Legacy Construction, Inc. in the Amount of $1,598,202 for the King
Street Urban Greening Project with an Estimated Construction Delivery Cost
of $1,918,240 (Project No. 23-6625) (Non-General Fund)
Department(s): Public Works Agency
Recommended Action:
1. Approve an appropriation adjustment to recognize $275,000 of prior year
fund balance in the Federal Clean Water Protection fund, Prior-Year
Carryforward revenue account (No. 05717002-50001) and appropriate the
same amount into the Federal Clean Water Protection Enterprise,
Improvements Other Than Building expenditure account. (Requires five
affirmative votes)
2. Approve an appropriation adjustment to recognize $300,000 of prior-year
fund balance in the Residential Development District 1, Park Acquisition &
Development Fees, Prior Year Carryforward revenue account (No. 31113002-
50001) and appropriate the same amount into the Residential Development
District 1, Improvements Other Than Building expenditure account. (Requires
five affirmative votes)
3. Approve an amendment to the Fiscal Year 2023-24 Capital Improvement
Program to add $275,000 of Federal Clean Water Protection Enterprise
funding and $300,000 of Residential Development District 1, Park Acquisition
& Development funding for the King Street Urban Greening Project (23-6625).
4. Award a construction contract to C.S. Legacy Construction, Inc., the lowest
responsible bidder, in accordance with the base bid in the amount of
$1,598,202, subject to change orders (not to exceed 25 percent of the base
bid amount) in accordance with the Greenbook: Standard Specifications for
Public Works Construction, for construction of the King Street Urban Greening
Project, for the term beginning October 17, 2023 and ending upon project
completion, and authorize the City Manager to execute the contract subject to
non-substantive changes approved by the City Manager and the City Attorney.
5. Approve the Project Cost Analysis for a total estimated construction
delivery cost of $1,918,240, which includes $1,598,202 for the construction
contract, $159,820 for contract administration, inspection, and testing, and a
$160,218 project contingency for unanticipated or unforeseen work.
6. Determine that the recommended actions are exempt from further review in
accordance with the California Environmental Quality Act (“CEQA”) as
Categorical Exemption Environmental Review No. ER-2023-73 was filed for
this project.