Item
46. Martin Luther King, Jr. Medical Campus Clinical Laboratory and Red-Bag
Storage Project Construction Contract
Recommendation: Find that the recommended actions are within the scope of
the Board’s previous finding of exemption from the California Environmental
Quality Act for the Martin Luther King, Jr. Medical Campus Clinical Laboratory
and Red-Bag Storage Project, Capital Project No. 69857 (Project) (2); approve
the revised Project budget of $16,975,000, an increase of $1,075,000 from the
previous Board-approved amount of $15,900,000, for the Project; approve the
Fiscal Year 2023-24 appropriation adjustment to allocate $1,075,000 from the
Department of Health Services’ Enterprise Fund Committed for the Department
of Health Services to fund the remaining project expenditures of the Project;
and authorize the Director of Public Works to finalize negotiations and execute
change orders with AWI Builders, Inc. as detailed below. (Department of
Public Works) APPROVE 4-VOTES
In an amount not to exceed $510,000 for building modifications due to a
change in laboratory equipment;
In an amount not to exceed $250,000 for changes required to the
Red-Bag Storage area foundation;
In an amount not to exceed $315,000 for additional rooftop equipment
pads; and
In an amount not to exceed $200,000 for revisions and additions of
low-voltage equipment. (23-3722)