Order of Business 8
e. Glendale Water and Power, re: City Owned Solar Development Program – Phase 1
Award of Contracts
1. Motion authorizing the City Manager, or his designee, to execute a construction
contract with Solar Optimum, Inc., using the Alternative Project Delivery Method for
the Engineer-Procure-Construct (EPC) of Solar PV Systems for a not-to-exceed
amount of $9,953,000 with a 15% contingency of $1,492,950 at the following project
sites: 1) Sports Complex, 2) Glendale Community College Lot 34, 3) Utility Operations
Center, 4) Central Library, and 5) GWP Perkins Building
2. Motion authorizing the City Manager, or his designee, to execute a contract with
Motive Energy Storage Systems, Inc., using the Alternative Project Delivery Method
for the EPC of Solar PV Systems for a not to exceed amount of $151,274 with a 15%
contingency of $22,691 for project design and engineering, and environmental
analysis under California Environmental Quality Act (CEQA) at the following project
site: 1) Brand Landfill
3. Resolution amending Resolution 23-24, authorizing the General Manager of Glendale
Water & Power Department, or his designee, to utilize the Engineer, Procure,
Construct (EPC) Project Delivery Method for the Solar Photovoltaic System at Six
Proposed Sites