7. Resolution to Amend the FY 2023-24 Capital Improvement Program (CIP) Budget by
Unappropriating Funds from Various Projects, and Appropriating These Funds and ATP
Cycle 4 Grant Funds to “Pomona Multi-Neighborhood Pedestrian and Bicycle
Improvements,” Project No. 428-2590-XXXXX-67930; and Awarding a Construction
Contract to Gentry Brothers, Inc.
It is recommended that the City Council take the following actions:
1) Adopt the following resolution:
RESOLUTION NO. 2023-231 - A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF POMONA, CALIFORNIA, TO AMEND THE FY 2023-24 CAPITAL
IMPROVEMENT PROGRAM (CIP) BUDGET BY UNAPPROPRIATING FUNDS
FROM VARIOUS PROJECTS AS INDICATED IN ATTACHMENT NO. 1 - EXHIBIT 1
TO RESOLUTION AND APPROPRIATING THESE FUNDS TO “POMONA
MULTI-NEIGHBORHOOD PEDESTRIAN AND BICYCLE IMPROVEMENTS,”
PROJECT NO. 428-2590-XXXXX-67930; AND BY ACCEPTING, INCREASING
REVENUE ESTIMATES, AND APPROPRIATING $8,534,000 OF ATP CYCLE 4
GRANT FUNDS TO “POMONA MULTI-NEIGHBORHOOD PEDESTRIAN AND
BICYCLE IMPROVEMENTS,” PROJECT NO. 428-2590-XXXXX-67930
2) Award a Construction Contract to Gentry Brothers, Inc. in the amount of $15,022,039
to include Base Bid plus Additive Alternates one (1) through five (5) for “Pomona
Multi-Neighborhood Pedestrian and Bicycle Improvements,” Project No.
428-2590-XXXXX-67930;
3) Authorize the City Manager, or his designee, to execute the construction contract, and
all related documents (ATP Cycle 4 Grant documents, permits, etc.);
4) Find that the project referenced above is categorically exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301(c) and that the
proposed project will not have a significant effect on the environment; and
5) Approve including Saturdays in the “Allowed Working Days” for the Contractor to
perform construction improvements, as necessary.