Agenda Item
· Signal Hill
City Council — Item a
Original agenda text
Order of Business 5
a. PRESENTATION - CIVIC CENTER MASTER PLAN PRELIMINARY DESIGN
OPTIONS
Summary:
On July 25, 2023, the City hired John Kaliski Architects, Incorporated (JKA) to
prepare the Civic Center Master Plan. Work began in August 2023, and a series
of community engagement efforts have taken place to date; including regular
social media and website postings and updates; two on-line surveys; pop-up
events at summer concert; Halloween festival and tree lighting; three-day design
workshop and community meeting in October; and several
Commission/Committee meetings (Sustainable City Committee - October 3,
2023; Planning Commission - October 17, 2023; Parks and Recreation
Commission- October 18, 2023; and Diversity Coalition Committee- October 19,
2023). Additional stakeholder meetings have also taken place with City staff,
and community groups such as the Long Beach Symphony. Following the
community and stakeholder input efforts, JKA prepared three preliminary design
options for City Council review and input with the goal of selecting one preferred
design alternative. Staff will make a final presentation on the selected design
and updated costs and schedule during the first quarter of 2024.
Strategic Plan Goal(s):
Goal No. 3 Economy: Improve the local economy, support local businesses,
and create a vibrant downtown core.
Goal No. 4 Infrastructure: Maintain and improve the City’s physical
infrastructure, water system, and recreational spaces.
Goal No. 5 High-Functioning Government: Strengthen internal communication,
recruitment, retention, systems and processes to increase the
effectiveness and efficiency of City services.
Recommendation:
Staff requests the City Council review and provide feedback regarding the
preliminary design options, select preferred design elements, and provide
direction to staff regarding a proposed phasing and funding model.