Board of Public Works — Item 15
Original agenda text
Item
(15)
BPWÂ2024Â0015
CD 6
REVISED BUDGET AND SUPPLEMENTAL AGREEMENT CHANGE ORDERS â FORD
E.C. â DONALD C. TILLMAN WATER RECLAMATION PLANT BERM IMPROVEMENTS
Recommending the Board:
1. AUTHORIZE $786,200 in additional contingency and approve a revised
construction budget of $8,009,000 for the Donald Tillman Water Reclamation
Plant Berm Improvements; and
2. AUTHORIZE the City Engineer to issue Change Order Nos. 26 through 32
and Nos. 35 through 42 to compensate the Contractor for extra work
resulting from differing site conditions and ownerÂdirected additions and
modifications; and
3. AUTHORIZE the City Engineer to issue Supplemental Agreement Change
Order No. 34 to Ford E.C. for a notÂtoÂexceed amount of $25,000 for the
Project to modify fencing on the western berm wall and issue additional
1. AUTHORIZE $786,200 in additional contingency and approve a revised
construction budget of $8,009,000 for the Donald Tillman Water Reclamation
Plant Berm Improvements; and
2. AUTHORIZE the City Engineer to issue Change Order Nos. 26 through 32
and Nos. 35 through 42 to compensate the Contractor for extra work
resulting from differing site conditions and ownerÂdirected additions and
modifications; and
3. AUTHORIZE the City Engineer to issue Supplemental Agreement Change
Order No. 34 to Ford E.C. for a notÂtoÂexceed amount of $25,000 for the
Project to modify fencing on the western berm wall and issue additional
separate change orders; and
4. AUTHORIZE two members of the Board to sign the Supplemental
Agreement Change Order No. 34; and
5. AUTHORIZE the City Engineer to issue subsequent change orders under the
Contract, up to the revised construction budget of $8,009,000 for the Project.
(W.O. SZD11286, CÂ139912)