City Council — Item 21
Original agenda text
Item
21. CONTRACT AMENDMENT: BICYCLE AND PEDESTRIAN IMPROVEMENT PLAN
CONSULTING SERVICES – F2M22-33, C2M22-39, M2M24-36
9
2-26-24
On January 8th and February 12th 2024, staff presented the draft Bike and Pedestrian
Improvement Plan for the Council’s consideration. After considerable public comment
regarding the Plan’s details and pursuant to requests for additional review, the Council
tabled the adoption of the Bicycle and Pedestrian Improvement Plan to March 11, 2024.
Beyond the original scope of work, the consultant conducted a virtual workshop on
January 23, 2024; a special meeting with the Transportation Commission on January 24,
2024; and an in-person workshop at the Library on February 1, 2024. In addition, on
February 12, 2024, it was requested the consultant engage in discussion with Asian
Pacific Islander Forward Movement (APIFM) to receive other public feedback regarding
the City’s draft Plan. Staff is requesting the City Council authorize an appropriation of
funds for the additional costs of $23,655 for the extended public review period of the Plan
(and subsequent Plan Drafts) under Measure M for a total contract expense of
$273,648.90.
Recommended Action: City Council approve a second amendment, subject to final
language approval by the City Manager and City Attorney, to the contract by and between
the City of Alhambra and Alta Planning + Design (C2M22-39) for the development of the
City’s Bicycle and Pedestrian Improvement Plan in an amount not to exceed $23,655 for
additional public outreach during the months of January, February and March 2024;
authorize an additional appropriation of $23,655 under Measure M for the added scope of
work; and, direct staff to undertake the steps necessary to finalize Council’s action.
(M2M24-36)