6D. AWARD OF CONSTRUCTION CONTRACT FOR THE FY 2022/23 CITYWIDE
STREET RESURFACING PROJECT (TASK CODE 2023-101)
Six bids for the FY 2022/23 Citywide Street Resurfacing Project were opened on
February 13, 2024. Based on the post-bid analysis of the bids received, staff has
determined the bid submitted by Onyx Paving Company, Inc. to be the lowest
responsible and responsive bid at $1,151,000.
RECOMMENDED ACTION:
1. City Council declare that this project is exempt from the California Environmental
Quality Act (“CEQA”), Class 1, Section 15301(c) as repair, maintenance, and minor
alteration of existing public structures; and
2. Award a construction contract for the FY 2022/23 Citywide Street Resurfacing
Project to Onyx Paving Company, Inc. for the bid amount of $1,151,000.00 and
reject all other bids; and
3. Authorize the City Manager to bind the City of Stanton and Onyx Paving Company,
Inc. in a contract for the construction; and
4. Authorize the City Manager to approve contract changes, not to exceed 10-percent
of the bid amount ($115,100).