6F. ACCEPTANCE OF THE 2023 CATCH BASIN SCREEN INSTALLATION PROJECT
BY THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The 2023 Catch Basin Screen Installation Project consisting of the installation of new
connector pipe screen (CPS-MODTM) and Grated Inlet Trash Screens (GITSTM) devices
in catch basins is now complete. The final construction cost for the project was $42,840,
coming in under budget below the contract award amount. The City Engineer certifies
that the work was satisfactorily completed as of February 5, 2024 and recommends that
the City Council accept the completed work performed on this project.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 1, and Section 15301(b) as minor alteration of
existing public utility; and
2. Accept the completion of improvements for the 2023 Catch Basin Screen Installation
Project, as certified by the City Engineer, and affix the date of February 5, 2024 as
the date of completion of all work on this project; and
February 27, 2024
3. Approve the final construction contract amount of $42,840 with G2 Construction,
Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the
Notice of Completion (Attachment) with the County Clerk-Recorder of the County of
Orange; and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to G2
Construction, Inc. in the amount of $2,142.