Order of Business 13
a. PUBLIC WORKS CONTRACT WITH PALP, INCORPORATED, DBA EXCEL
PAVING COMPANY (EXCEL PAVING) FOR THE PAVEMENT MANAGEMENT
PROGRAM - CHERRY AVENUE AND JESSIE NELSON CIRCLE
IMPROVEMENTS PROJECT
Summary:
The City Council will consider entering into a Public Works Contract with Excel
Paving for the construction of the Cherry Avenue and Jessie Nelson Circle
Improvements Project. The Project includes the repair of approximately 85,000
square feet of asphalt pavement on Cherry Avenue between Hill Street and
Burnett Street. The pavement repair strategies for the Project consists of street
reconstruction and 2” grind and overlay, the application of approximately 13,300
square feet of Type II slurry seal coating, on Jessie Nelson Circle, and the
restoration of traffic striping and markings.
Strategic Plan Goal(s):
Goal No. 4 Infrastructure: Maintain and improve the City’s physical
infrastructure, water system and recreational spaces.
Recommendations:
1. Authorize the City Manager to enter into a Public Works Contract with Excel
Paving for the construction of the Cherry Avenue and Jessie Nelson Circle
Improvements Project, for a term of 21 calendar days and a not-to-exceed
contract amount of $321,876.60, in a form approved by the City Attorney.
2. Authorize a contingency of 10% ($32,188) and up to a 30-calendar day
extension to accommodate additional scope of work and changed or
unforeseen conditions, to be utilized if approved by the Public Works
Director, for a total construction budget of $354,064.60.