South El Monte
City Council
7.h. CONSIDERATION AND APPROVAL OF RESOLUTION NO. 24-134,
APPROVING PLANS AND SPECIFICIATIONS AND AWARDING
CONSTRUCTION CONTRACT TO PRO FLOORING CORPORATION
FOR THE COMMUNITY CENTER BASKETBALL GYM FLOORING
IMPROVEMENTS PROJECT
On January 10, 2024, the Engineering Department solicited bids for the
Community Center Basketball Gym Flooring Improvements Project. The
bid opening date was February 13, 2024, at 2:00 PM. The scope of work
includes but not limited to the removal and disposal of existing flooring and
installation of new basketball gym multi-use resilient wood flooring. The
lowest responsive bid was submitted by Pro Flooring Corporation in the
amount of $128,320.
RECOMMENDED ACTION: Staff recommends City Council:
1. Review the bids and find that Pro Flooring Corporation has submitted
the lowest responsive bid;
2. Adopt Resolution No. 24-134, approving plans and specifications for
the Community Center Basketball Gym Flooring Improvements Project
and awarding a contract to Pro Flooring Corporation in the amount of
$128,320;
3. Approve a 15% contingency amount of $19,248 for a total project
construction budget amount not to exceed $147,568; and
4. Authorize the City Manager or designee to negotiate and execute the
agreement.