48. Boilers and Chillers Replacement Project Contract
Recommendation: Approve a revised project budget of $96,100,000, an
increase of $50,000,000 from the previous Board-approved amount of
$46,100,000, to procure long-lead mechanical and electrical equipment
(Equipment) for the Civic Center Central Plant Boilers and Chillers Replacement
Project, Capital Project No. 87735 (Project) (1); approve an increased
authorization of $36,000,000 for the Interim Director of Internal Services, as the
County's Purchasing Agent, to carry out the procurement and acquisition of the
Equipment for the Project; and find that the recommended actions are within the
scope of the previous exemption from the California Environmental Quality Act
for the approved Project. (Department of Public Works) APPROVE