19. Progress and Adaptive Management of the Safe Clean Water Program
Recommendation as submitted by Supervisor Horvath: Instruct the Director of
Public Works to report back to the Board in 90 days , on the progress and
timeline for completion of the following, with a target date no later than June
2025:
Indicators and targets for the Safe, Clean Water Program (SCWP), to
be developed with the Regional Oversight Committee (ROC), that can be
used to measure achievement of SCWP goals, guide watershed
planning, and inform project development, solicitation, and evaluation
efforts;
Precise metrics, updated definitions of Local Water Supply Benefit,
Nature-Based Solutions, Disadvantaged Community Benefit, and Local
Water Supply Benefit, dry- and wet-weather water quality, and scoring
criteria that better align with the SCWP goals;
Watershed planning efforts, including data and a gap analysis,
community needs assessment, including engagement with the Watershed
Area Steering Committee (WASC), and alignment with the plan to
capture 300,000 acre-foot per year of new stormwater by 2045;
Revised Regional Program application processes, feasibility study
guidelines, and scoring criteria to account for additional performance
indicators and distinct project phases, including the required public
processes and input from the governing bodies as appropriate;
Revised Regional Program Transfer Agreements , to better align with
distinct project phases like design, construction, and maintenance, and
with the transfer Agreement revisions to be brought back to the Board for
approval;
Updated or new guidance documents, tools, and information for
governance bodies and project developers to facilitate achievement of
performance indicators and targets;
Updated strategies for monitoring of completed projects towards meeting
stated project goals and a regular update with cumulative findings on
impacts, including any related recommendations for adaptive
management of the program to maximize program outcomes;
Guidance and recommendations to WASCs for managing cost overruns
and project modification requests in the context of watershed planning
and constrained funding availability in certain watersheds;
An assessment of community engagement processes to date and how
they could be improved upon, including strategies to better engage small
cities, tribal interests, community -based organizations, and others who
have been less involved or underrepresented;
An assessment of viability and potential responsibilities of a scientific or
technical advisory committee for the SCWP, specifically for review and
recommendations for scientific studies;
An assessment of viability and a strategy to fund scientific studies that
have Countywide significance without requiring approval of every
WASC;
Collaboration with, and funding of, the Department of Economic
Opportunity to design and implement Workforce Development program(s)
to support SCWP goals, with corresponding workforce requirements to
be integrated into Feasibility Study Guidelines, Project Modules, and
Transfer Agreements;
District Public Education programs, including progress of Public
Education and Community Engagement Grants Program and investments
in school curricula;
A report back to the Board on strategies and best practices for engaging
school campuses in implementing stormwater capture projects that help
achieve schoolyard transformation, greening, cooling, and other benefits
in concert with the water supply, water quality, and multi-benefit goals of
the SCWP, including best practices for integration of school projects with
school curriculum, such as those being developed and/or funded as part
of the District Education Programs; and
Ongoing communication and consultation with the WASCs and ROC in
the development of new policies and programs;
Instruct the Chief Engineer of the County Flood Control District to work with
County Counsel to prepare amendments to the Safe Clean Water Program
Ordinance to amend Section 18.07 of the Safe, Clean Water Implementation
Ordinance to authorize the Chief Engineer to request proposals for new
projects, project concepts, and scientific studies for inclusion in Stormwater
Investments Plans on either an annual or biennial basis; amend Sections 18.07,
18.08 and 18.09, to change the frequency of progress and expenditure
reporting from quarterly to semi-annually, and to clarify that certain County
Flood Control District’s responsibilities are carried out by the Chief Engineer;
Instruct the ROC to provide further recommendations to the Board to improve
the efficacy and accelerate project delivery of the SCWP by the end of 2024;
and
Thank the members of the ROC, Scoring Committee, and nine WASCs, for
their service during the first four years of the program , and congratulate the
newly appointed community leaders that will help to actively manage the
program moving forward. (24-1010)