Agenda Item
· Newport Beach
City Council — Item 4
Original agenda text
Item
4. Underground Utility Assessment District No. 111, Underground Utilities
District No. 22 Phase 2 & 3, & Utility Undergrounding for McFadden Alleys
and Court Street - Notice of Completion for Contract No. 7833-1 (21A11)
a) Accept the completed work and authorize the City Clerk to file a Notice of
Completion for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after
the Notice of Completion has been recorded in accordance with applicable portions
of Civil Code;
c) Release Faithful Performance Bond one year after acceptance by the City
Council;
d) Authorize staff to proceed with the final Verizon additional work and increase
project contingency from $3,500,000 to $3,595,003 (approximately 51.6 percent of
the contract award) to cover the additional cost of the requested additional work; and
e) Approve Budget Amendment No. 24-058 recognizing $31,872.75 in contribution
revenue from Crown Castle to Account No. 13501-561007-21A11 and $159,250.85
in increased expenditures in Account No. 13501-980000-21A11 (UUD22-1 CIP
Expenditures for GL) from multiple utility companies.
Staff Report
Attachment A - Location Map
Attachment B - Budget Amendment
March 26, 2024