Agenda Item
· West Hollywood
City Council — Item A
Original agenda text
New Business
6.A. CONSTRUCTION AGREEMENT WITH BALI CONSTRUCTION TO
CONSTRUCT CIP 2204, RULE 20B OVERHEAD TO UNDERGROUND
CONVERSION LA PEER DR. & ALMONT DR.; AMENDMENT NO. 2 TO
THE AGREEMENT FOR SERVICES WITH MAGNA CONSULTING &
DESIGN FOR ENGINEERING SERVICES; AND AMENDMENT NO. 3 TO
THE AGREEMENT FOR SERVICES WITH BERG & ASSOCIATES FOR
CONSTRUCTION MANAGEMENT & INSPECTION SERVICES [S.
CAMPBELL, J. GILMOUR]:
SUBJECT: The City Council will consider approval of a construction
Agreement with Bali Construction to construct CIP 2204, Rule 20B
Overhead to Underground Conversion La Peer Dr. & Almont Dr.;
amending the Agreement for Services with Magna Consulting & Design for
engineering services; and amending the Agreement for Services with Berg
& Associates for construction management and inspection services.
RECOMMENDATIONS: 1) Approve a Construction Agreement with Bali
Construction, in the amount of $3,572,236 for the construction of CIP
2204, Rule 20B Overhead to Underground Conversion La Peer Dr. &
Almont Dr., and authorize the City Manager or designee to execute
documents incident to the Agreement; 2) Authorize the City Engineer to
approve change orders to the Construction Agreement in an amount not to
exceed 20% ($714,447.20) of the total Agreement amount; 3) Approve
Amendment No. 2 to the Agreement for Services with Magna Consulting &
Design to increase the amount of the Agreement by $48,087, for a total
not-to-exceed amount of $180,053, and to extend the Agreement to June
30, 2026, and authorize the City Manager or designee to execute
documents incident to the Agreement; 4) Approve Amendment No. 3 to
the Agreement for Services with Berg & Associates to increase the
amount of the Agreement by $1,058,553.50, for a total not-to-exceed
amount of $4,337,137.26, and to extend the Agreement to June 30, 2026,
and authorize the City Manager or designee to execute documents
incident to the Agreement; 5) Authorize the City Manager or designee to
enter into Agreements for Services with various Utility Agencies to
facilitate the Project in an amount not-to-exceed $500,000; 6) Authorize
the Director of Finance & Technology Services to allocate $4,411,000.00
from unallocated reserves in the Debt Funded Capital Projects Fund for
construction of CIP 2204, Rule 20B Overhead to Underground Conversion
La Peer Dr. & Almont Dr and related costs; and 7) Adopt Resolution
No. 24-_________: “A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF WEST HOLLYWOOD APPROVING THE DESIGN AND PLANS
FOR THE CONSTRUCTION OF CIP 2204, RULE 20B OVERHEAD TO
UNDERGROUND CONVERSION LA PEER DR. & ALMONT DR,
PURSUANT TO GOVERNMENT CODE SECTION 830.6”.