9. Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot Project (15T09) -
Approval of Additional Construction Contingency with Reyes Construction
(Contract No. 8020-6), and Approval of Amendment No. Two to Professional
Services Agreement with Ardurra (Contract No. 8020-8) and Amendment No.
Five to Professional Services Agreement with Dokken Engineering (Contract
No. 8020-5)
a) Determine this action is exempt from the California Environmental Quality Act
(CEQA) pursuant to Sections 15060(c)(2) and 15060(c)(3) of the CEQA Guidelines
because this action will not result in a physical change to the environment, directly or
indirectly;
b) Approve Budget Amendment No. 25-005, transferring $805,874 from the
unappropriated FFP: Parks/Community Centers fund balance into Account No.
56201-980000-15T09;
c) Increase the construction contract contingency by $500,000 to $1,342,000
(approximately 12.8% of the contract award amount) with Reyes Construction
(Contract No. 8020-6) to cover additional costs associated with unforeseen field
conditions;
d) Authorize payment of $54,583.54 from the CIP Storm Drain Repair Account No.
01201926-980000-25D02 (Neighborhood Enhancement funds) to T.E. Roberts
under its existing on-call contract;
e) Approve Amendment No. Two to Professional Services Agreement with Ardurra
(Contract No. 8020-8) for construction oversight of the Superior Avenue
Pedestrian/Bicycle Bridge and Parking Lot project in the amount of $286,874 for a
total not-to-exceed amount of $1,537,020, and authorize the Mayor and City Clerk to
execute the amendment; and
f) Approve Amendment No. Five to Professional Services Agreement with Dokken
Engineering (Contract No. 8020-5) for additional design services for the Superior
Avenue Pedestrian/Bicycle Bridge and Parking Lot project in the amount of $19,000
for a total not-to-exceed amount of $2,121,499, and authorize the Mayor and City
Clerk to execute the amendment.