a. PUBLIC WORKS CONTRACT WITH MAJ ENGINEERING FOR THE ADA
CURB RAMP INSTALLATION PROJECT
Summary:
The City Council will consider entering into a Public Works Contract with MAJ
Engineering for the Americans with Disabilities Act, ADA, Curb Ramp Installation
Project. This project consists of the construction of ten new ADA compliant
Ramps at various locations within the City). This project is federally funded by a
Community Development Block Grant (CDBG)
Strategic Plan Goal(s):
Goal No. 4 Infrastructure: Maintain and improve the City’s physical
infrastructure, water system and recreational spaces.
Recommendations:
1. Authorize the City Manager to enter into a Public Works Contract with MAJ
Engineering for the construction of the ADA Curb Ramp Installation Project
for a term of 30 calendar days and a not-to-exceed contract in the amount of
$135,814.00, in a form approved by the City Attorney.
2. Authorize a contingency of 10% ($13,581) and up to a 30-day extension to
accommodate the additional scope of work and any unforeseen conditions.
The proposed contingency amount, subject to the approval of the Public
Works Director, brings the total construction budget to $149,395.