Item
9. RESOLUTION NO. ____________ - APPROVE TWELFTH AMENDMENT TO PERMIT NO.
733 WITH FENIX MARINE SERVICES, LTD.
Summary: Staff requests approval of the Twelfth Amendment (Amendment) to Permit No. 733
(Permit) with Fenix Marine Services, Ltd. (FMS) which is necessary for the City of Los Angeles
Harbor Department (Harbor Department) to undertake construction of the Berths 302-305 On-Dock
Rail Yard Expansion Project (Project). The proposed Project will add five loading/unloading tracks
to the FMS terminal located at Pier 300, which will increase on-dock railyard capacity and enable
more cargo to be loaded onto trains via the on-dock railyard within the terminal. The Project cost is
$51,900,000 of which, $37,378,743 will be funded through State and Federal grants secured by the
Harbor Department. The Amendment makes the following notable changes to the Permit: 1) defines
the Project scope; 2) temporarily removes approximately 23 acres of the premises for the duration
of the 24-month construction period and provides substitute premises adjacent to the terminal; 3)
modifies rent provisions and adds potential rent credits and damages clauses, all related to the
Project; 4) increases the premises size from 292 acres to 302 acres at Project completion; 5)
designates the rail added under the Project as a new parcel at a new fixed rate; and 6) adds Project-
specific indemnity provisions. The Harbor Department will be financially responsible for potentially
$27,551,257 in costs, summarized as follows: payment of the $14,521,257 in remaining costs
related to the Project; providing rent credits in the amount of $10,230,000; providing an additional
rent credit not-to-exceed $1,000,000 arising from increased FMS operating costs during
construction; as well as for payment of liquidated damages not-to-exceed $1,800,000 to FMS
resulting from Project construction delays.
Recommendation: Board to resolve (1) find that the Director of Environmental Management has
determined that the proposed action has been previously evaluated pursuant to the requirements
of the California Environmental Quality Act (CEQA) under Article II Section 2(i) of the Los Angeles
City CEQA Guidelines; (2) approve the Twelfth Amendment to Permit No. 733 with Fenix Marine
Services, Ltd.; (3) direct the Board Secretary to transmit the Twelfth Amendment to Permit No. 733
to City Council for approval pursuant to Charter Section 606 of the City Charter; (4) authorize the
Executive Director to execute and the Board Secretary to attest to the Twelfth Amendment upon
approval by City Council; and (5) adopt Resolution No. ___________.