64. Marina del Rey Back Basins Stormwater Improvements Project
Construction Contract
Recommendation: Establish and approve the Marina del Rey Back Basins
Stormwater Improvements Project, Capital Project (CP) No. 69881 (Project)
in the unincorporated community of Marina del Rey (2), with a total Project
budget of $4,134,000; approve an appropriation adjustment to transfer
$1,024,000 from the Unincorporated Area Stormwater Quality
Improvements, CP No. 87195, to fully fund the proposed Project; adopt the
plans and specifications that are on file for the Project; advertise for bids to
be received before 11:00 a.m. on October 16, 2024; find pursuant to State
Public Contract Code, Section 3400 (c) (2) and (3), that it is necessary to
specify designated items by specific brand name in order to match other
products in use on a particular public improvement either completed or in
the course of completion, and to obtain a necessary item that is only
available from one source; find that the proposed Project is exempt from the
California Environmental Quality Act; and authorize the Director of Public
Works to take the following actions: (Department of Public Works)
APPROVE
Determine whether the bid of the apparent responsible contractor
with the lowest apparent responsive bid is, in fact, responsive and, if
not responsive, determine which apparent responsible contractor
submitted the lowest responsive bid, waive inconsequential and
nonmaterial deficiencies in bids submitted, and determine, in
accordance with applicable contract and bid documents, whether the
apparent lowest responsive and responsible bidder has satisfied all
conditions for contract award;
Award and execute a construction contract for the Project to the
responsible contractor with the lowest responsive bid within the
approved total budget; and
Extend the date and time for the receipt of bids, allow substitution of
subcontractors and relief of bidders, approve and execute change
orders within the same monetary limits delegated to the Director,
accept the Project upon its final completion, and release retention
money withheld. (24-3695)