13. CONTRACT WITH SANCON TECHNOLOGIES, INC. FOR MISCELLANEOUS
STORM DRAIN LINING
Proposed Motion:
1. Approve plans and specifications for the Miscellaneous Storm Drain Lining Project.
2. Approve $485,000 budget transfer and appropriation of Drainage Capital Outlay
Funds (Fund 74) from Project 52591 Annual Storm Drain Repair to Project 52020
Miscellaneous Storm Drain Lining within the Capital Projects Fund (Fund 74).
3. Award $385,284 construction contract for Miscellaneous Storm Drain Lining Project to
Sancon Technologies, Inc. and authorize City Manager, or designee, to execute and
administer the contract, in a form approved by the City Attorney.
4. Authorize Public Works Director, or designee, to approve any future change orders for
construction and professional engineering construction support services within the
approved project budget.
September 17, 2024 - Page 5