7. Award of Construction Contract to WGJ Enterprises, Inc. dba PCI for the
Bicycle Green Zone Pilot Project, Cash Contract No. 23-16
Recommendation
Staff recommends that the City Council:
1. Award the Construction Contract for the Bicycle Green Zone Pilot Project,
Cash Contract No. 23-16 to WGJ Enterprises, Inc. dba PCI in the amount
of $254,057;
2. Authorize the Public Works Director/City Engineer to process change
orders in an amount not to exceed 20% of the contract for $50,811, for a
total not-to-exceed amount of $304,868, if needed;
3. Authorize the City Manager to execute the Construction Contract for the
Bicycle Green Zone Pilot Project, Cash Contract No. 23-16 to WGJ
Enterprises, Inc. dba PCI, subject to the City Attorney making non-
substantive changes; and,
4. Authorize the Public Works Director/City Engineer to execute the Notice of
Completion at the conclusion of construction.