Agenda Item
· San Diego
City Council — Item 103
Original agenda text
Item
Item 103: Award of Design-Build Phase-Funded Contract Agreement K-24-2131-
DB2-3-C with Barnhart-Reese Construction for the Oak Park Library
Project.
Total Estimated Cost of Proposed Action and Funding Source:
The total phase-funded cost is $34,900,000.00; of which $4,621,096 is for
Phase 1 and $30,278,904.00 for all subsequent phases. A $20,000,000
California State Grant Fund is being utilized to award phase 1 of the design-
build contract for the Oak Park Library project.
Council District(s) Affected: 4.
Proposed Actions:
(R-2025-189)
Resolution authorizing the Mayor, or his designee, to enter into a contract
with Barnhart-Reese Construction, in an amount not-to-exceed $34,900,000,
to provide design and construction services for Oak Park Library and related
actions.
Committee Actions Taken:
This item was heard at the Active Transportation and Infrastructure
Committee meeting on October 9, 2024.
ACTION: Motion by Committee Member Foster III, second by Chair Whitburn,
to recommend Council approval of staff’s proposed actions.
VOTE: 3-0; Whitburn-yea, LaCava-yea, Foster III-yea, von Wilpert-not present.
(Rev. 10/24/24)
Engineering & Capital Projects: Jason Grani, (619) 533-7525
City Attorney Contact: Dana C. Fairchild