Agenda Item
· Coronado
City Council — Item f
Original agenda text
Order of Business 5
f. ADELLA AND YNEZ UNDERGROUNDING PROJECT: ACCEPT THE SDGE
COST ESTIMATE OF $990,760 FOR THE SDGE PORTION OF
UNDERGROUNDING OF OVERHEAD FACILITIES; AND AUTHORIZE THE
CITY MANAGER TO ENTER INTO AGREEMENTS WITH UTILITY
PROVIDERS
Recommendation:
1. Find the proposed undergrounding of overhead facilities on Adella Lane and
Ynez Place exempt from CEQA pursuant to State CEQA Guidelines section
15302; accept the SDGE cost estimate of $990,760 for the SDGE portion of
undergrounding of overhead facilities; authorize the City Manager to enter
into an agreement with SDGE and provide a deposit in said amount; initiate
City of Coronadojoint trench offers with AT&T and Charter Communications; enter into Page 3
agreements with AT&T and Charter Communications including any
fees/deposits; all in a form as approved by the City Attorney.
2. Authorize the City Manager to enter into any other agreements and to
COST ESTIMATE OF $990,760 FOR THE SDGE PORTION OF
UNDERGROUNDING OF OVERHEAD FACILITIES; AND AUTHORIZE THE
CITY MANAGER TO ENTER INTO AGREEMENTS WITH UTILITY
PROVIDERS
Recommendation:
1. Find the proposed undergrounding of overhead facilities on Adella Lane and
Ynez Place exempt from CEQA pursuant to State CEQA Guidelines section
15302; accept the SDGE cost estimate of $990,760 for the SDGE portion of
undergrounding of overhead facilities; authorize the City Manager to enter
into an agreement with SDGE and provide a deposit in said amount; initiate
joint trench offers with AT&T and Charter Communications; enter into
agreements with AT&T and Charter Communications including any
fees/deposits; all in a form as approved by the City Attorney.
2. Authorize the City Manager to enter into any other agreements and to
provide any other deposits/fees as required to continue the project all within
the project budget.