6. PROJECT NO. 7232 – APPROVAL OF CONSTRUCTION CONTRACT CHANGE ORDER FOR TRAFFIC
SIGNAL IMPROVEMENTS ON ALONDRA BOULEVARD FROM HOME DEPOT TO SHOEMAKER
AVENUE [FEDERAL PROJECT NO. HSIPL-5347(042)] – ENGINEERS REPORT 24-17
Staff recommends City Council approve an Amendment No. 2 to the agreement with Select Electric Inc. to
continue the scope of work of Construction for Project No. 7232 in an amount of $224,051.90 of Highway
Safety Improvement Program (HSIP) funds, which will increase the agreement amount from $1,595,850 to
$2,218,864.40; and authorize the City Manager to execute the amendment on behalf of the City, in a form
approved by the City Attorney.