Agenda Item · Norwalk

City Council — Item 6

Norwalk November 06, 2024 City Council Item 6
Original agenda text Consent Item
6. PROJECT NO. 7232 – APPROVAL OF CONSTRUCTION CONTRACT CHANGE ORDER FOR TRAFFIC SIGNAL IMPROVEMENTS ON ALONDRA BOULEVARD FROM HOME DEPOT TO SHOEMAKER AVENUE [FEDERAL PROJECT NO. HSIPL-5347(042)] – ENGINEERS REPORT 24-17 Staff recommends City Council approve an Amendment No. 2 to the agreement with Select Electric Inc. to continue the scope of work of Construction for Project No. 7232 in an amount of $224,051.90 of Highway Safety Improvement Program (HSIP) funds, which will increase the agreement amount from $1,595,850 to $2,218,864.40; and authorize the City Manager to execute the amendment on behalf of the City, in a form approved by the City Attorney.