9G. ACCEPTANCE OF THE CITYWIDE CONCRETE REPAIR PROJECT (TASK CODE NO.
2025-104) BY THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The Citywide Concrete Repair Project, consisting of the removing and replacing of various
concrete infrastructure such as sidewalks, curb & gutters, and driveway approaches
throughout the City, is now complete. The final construction cost for the project was
$203,949, less than the awarded contract amount and approved change order limit. The
City Engineer, in his judgment, certifies that the work was satisfactorily completed as of
December 12, 2024 and recommends that the City Council accept the completed work
performed on this project.
RECOMMENDED ACTION:
1. City Council declare this project categorically exempt under the California
Environmental Quality Act, Class 1, and 15301(c) as repair, maintenance, and minor
alteration of existing public structures; and
2. Accept the completion of improvements for the Citywide Concrete Repair Project, as
certified by the City Engineer, and affix the date of December 12, 2024 as the date of
completion of all work on this project; and
3. Approve the final construction contract amount of $203,949 with CJ Concrete
Construction, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion with the County Clerk-Recorder of the County of Orange; and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to CJ
Concrete Construction, Inc. in the amount of $10,197.45.