11.3 Aquatics Center Project Quarterly Update
RECOMMENDATION: It is staff's recommendation that the City
Council receive and file the March 2025 John Anson Ford Park
Regional Aquatics Center Improvements update report.
CONCLUSION: Staff will keep Council informed of the progress we
are making during construction and will continue to seek outside
funding sources to minimize the impact to the general fund.
FISCAL IMPACT: The Project budget is $31,270,000, consisting of the
following funds:
Land and Water Conservation Fund - $6 million (Federal)
Supervisor Janice Hahn - $4 million (County)
Assemblymember Cristina Garcia - $2 million (State)
Congresswoman Roybal-Allard - $1.5 million (Federal)
General Fund - $14.6 million (City)
The current estimated total Project costs are as follows:
Design (RJM Design Group) $1,045,100
Labor Compliance (Michael Baker International) $224,200
Construction Management & Inspection (Ardurra) $2,040,400
Construction Cost (Bernards) $26,334,000
Construction Change Orders (Bernards) $258,500
Remaining Construction Contingency $1,304,500
Publications & Misc. Costs $1,200
TOTAL ESTIMATED PROJECT COST $31,270,000
Annual staffing and operating costs of approximately $2,700,000 will
need to be included in future general fund budgets.